Class Q Agricultural Conversion
Class Q permitted development groundworks for agricultural building conversion to residential use in Liskeard, Cornwall
Project Overview
D Hall Plant Hire & Groundworks undertook a Class Q permitted development conversion of a disused agricultural barn (approximately 185 square meters) into 3 residential properties in Liskeard, Cornwall. Class Q is a form of permitted development allowing for the conversion of agricultural buildings to residential use for up to a maximum of 5 dwellings. The client had pre-completed internal fittings removal and floor lowering work before our involvement.
The structural work included concrete wall removal from east and west gables, concrete stanchion cutting and retention, perimeter foundation breaking and removal, and foundation digging for internal walls. We installed comprehensive drainage infrastructure for all three properties with inspection chambers, including a 12-person sewage treatment plant at depths exceeding 4 meters with concrete encasing and ring installation. All ducting for electricity, water, and sewage systems was installed along with three radon sumps and associated pipework.
The floor works comprised a 50mm concrete blinding layer, radon membrane installation using RIW blackjack and Visqueen tanking membranes, A252 reinforcing mesh with L-bars, and 150mm of C40 concrete for the new floor slab. We completed perimeter upstand shuttering and concrete casting, and excavated and trimmed one barn side to improve site access for subsequent trades. The project was completed using a 13-ton excavator and 9-ton dumper with full CDM compliant welfare facilities.
Key Work Completed
Concrete wall removal from east and west gables
Concrete stanchion cutting, squaring, and retention
Perimeter concrete foundation breaking and removal
Foundation digging for internal walls at varying widths
Drainage infrastructure for all 3 properties with inspection chambers
Installation of 12-person sewage treatment plant at 4m+ depth
Concrete encasing and ring installation for deep treatment plant
Ducting for electricity, water, and sewage systems
Three radon sumps with associated pipework
50mm concrete blinding layer
Radon membrane installation (RIW blackjack and Visqueen tanking)
A252 reinforcing mesh with L-bars
150mm C40 concrete floor slab
Perimeter upstand shuttering and concrete casting
Excavated and trimmed one barn side for trade access
Equipment Used
13-ton excavator
9-ton dumper truck
RIW blackjack tanking membrane
Visqueen tanking membrane
CDM compliant site welfare unit
Project Gallery

Original Barn Structure

Structural Alterations

Foundation Excavation

Drainage System

Sewage Treatment Plant

Radon Protection

Membrane Installation

Reinforcement Setup

Concrete Slab Pour

Perimeter Upstand

Construction Progress

Groundworks Complete

Ready for Construction