Exeter University Groundworks - Commercial Campus Infrastructure Devon

Exeter University Project

Commercial groundworks contract for Exeter University campus infrastructure development in Devon

📍 Exeter, Devon
🏗️ Commercial Project
Completed 2024

Project Overview

D Hall Plant Hire & Groundworks Ltd completed groundworks for a new Cryostore facility at Exeter University, working as a subcontractor to Mercury Construction. This project involved two distinct phases of specialized concrete work for the university's research infrastructure, with particularly challenging existing concrete conditions.

Phase 1 involved breaking out existing concrete surface, removing concrete waste, excavating trenches to specified depth, and coordinating with Kenex Engineering for steelwork installation. We applied D49 wrapping mesh to the steelwork, installed 20mm compressible isolation joints at trench edges, and filled with RC50XF concrete to structural specifications.

Phase 2 required breaking out some of the toughest concrete we had encountered in years for an additional 4m × 3.5m slab. After concrete waste removal, we installed H16 dowel bars, placed 20mm compressible isolation joints at the perimeter, and laid two layers of A393 mesh reinforcement before pouring RC50XF concrete with a brushed finish. The challenging conditions and specialist requirements showcased our expertise in complex university infrastructure projects.

Key Work Completed

Phase 1: Breaking out existing concrete surface (very tough conditions)

Removal of concrete waste from university site

Excavation of trenches to specified depth

Steelwork installation (supplied/fitted by Kenex Engineering)

Application of D49 wrapping mesh to steelwork

20mm compressible isolation joint at trench edges

Filling with RC50XF concrete

Phase 2: Breaking out challenging concrete for 4m × 3.5m slab

Installation of H16 dowel bars

20mm compressible isolation joint at perimeter

Two layers of A393 mesh reinforcement

RC50XF concrete with brushed finish

Equipment Used

Heavy-duty concrete breakers

Excavators for trench work

Concrete pumping equipment

Specialist breaking tools for tough concrete

Project Gallery

Initial concrete breaking at Exeter University Cryostore site

Concrete Removal

Trench excavation for Cryostore foundation Exeter University

Trench Excavation

Steelwork installation by Kenex Engineering with D49 mesh

Steelwork Installation

Compressible isolation joint and concrete preparation

Joint Preparation

RC50XF concrete pouring Cryostore facility

Concrete Pour Phase 1

Additional 4m x 3.5m slab excavation and preparation

Phase 2 Slab Prep

H16 dowel bars and A393 mesh reinforcement installation

Reinforcement Setup

Completed Cryostore groundworks with brushed finish Exeter University

Completed Groundworks